National Society for the
This page lists current & recent work being done on covered bridges or under design. If you are aware of any projects not included here, please notify us at nspcb@yahoo.com so they can be added.
For earlier entries, see the
list of major covered bridge projects since 2010.![]()
| California | Maine | New Hampshire | Pennsylvania |
| Illinois | Maryland | New York | Québec |
| Indiana | Missouri | Ohio | Vermont |
| Kentucky | New Brunswick | Ontario | West Virginia |
| World Guide Number | Last Updated | ||
|
Illinois |
|||
| IL/13-06-01 |
Red Bridge After being severely damaged by a tractor-trailer on November 16, 2023, a crew from the Illinois Department of Transportation installed temporary shoring in December 2023 to stabilize the roof. The structure was evaluated and repairs are underway. The project is expected to be completed in Spring 2027. |
Repairs Underway | October 8, 2026 |
|
Indiana |
|||
| IN/14-49-07 |
Traders Point Bridge On August 18, 2025, Indiana Landmarks announced that bridge was included on its annual compilation of the state’s "10 Most Endangered" landmarks. Originally built over Fishback Creek, it was moved about 0.6 miles to its present location in 1960. The bridge will be dismantled soon, repaired and reconstructed in Eagle Creek Park along a pedestrian walkway. |
Project to begin soon | October 28, 2026 |
| IN/14-61-05 |
Nevins Bridge The bridge was closed due to structural issues. An arch on the southwest corner of the bridge has failed, necessitating immediate repairs. No estimate when repairs will occur. |
Project Underway | October 8, 2026 |
| IN/14-61-21 |
Portland Mills Bridge The bridge has been closed due to the discovery of extensive termite damage on the lower chords around all of the arch terminals and on the arches themselves. The county estimates that repairs will cost $800,000 to $1 million. According to the minutes from the December 15, 2025 meeting, the county will be seeking federal funds for more substantial repairs. We have not received any updates since then. |
Repairs Anticipated | December 15, 2025 |
| IN/14-67-10 |
Oakalla Bridge The bridge has been closed due to “structural integrity issues”. All four arch ends are being replaced. Two of them had already failed and others were not in good condition. Some of the damage is thought to be the result of an overweight vehicle crossing, probably repeatedly. The strain has caused some unusual bending of the arches and damage to the vertical posts near the ends caused by excess force from the adjoining diagonal timbers. |
Repairs Underway | November 8, 2026 |
|
Kentucky |
|||
|
Maine |
|||
|
Maryland |
|||
|
Missouri |
|||
| MO/25-58-01 |
Locust Creek Bridge On February 26, 2025, the bridge was moved to a new
location in Pershing State Park where it will become the trailhead for the
park's riparian trail. It has been waiting for approach spans to be
constructed for over a year. |
Awaiting Repairs | October 26, 2026 |
|
New Brunswick |
|||
| NB/55-14-13 |
Wheaton or Tantramar River #2 Bridge The bridge was closed on July 11, 2024 due to safety concerns. The New
Brunswick Department of Transportation and Infrastructure is planning to
install a modular bridge next to it for traffic and restore the covered
bridge for pedestrian use. |
Bypass Planned | October 12, 2026 |
|
New Hampshire |
|||
|
New York |
|||
|
North Carolina |
|||
|
Ohio |
|||
| OH/35-05-06 |
Blackwood Bridge The extensive repairs to this bridge are now complete and the span was opened to traffic on September 18, 2026. Work included repairs to the trusses and abutments along with a new floor and new metal roof. |
Project Completed | September 18, 2026 |
|
Ontario |
|||
| ON/59-50-01 |
West Montrose Bridge Waterloo County, ON Repairs to this span have begun. The work will include removal of the steel Bailey truss which had provided part of the structures support along with other repairs. The project was advertised in spring 2025 and is expected to be completed in Spring 2027. |
Repairs Underway | October 8, 2026 |
|
Pennsylvania |
|||
| PA/38-09-05 |
South Perkasie Bridge Bucks County, PA On September 2, 2026, five years after the remnants of Hurricane Ida swept the bridge from its abutments, the long-awaited repair project was officially underway. The work will fix the bridge’s historic timber structure and place it on new abutments approximately 50 feet farther from the East Branch Perkiomen Creek to reduce the risk of future flood damage. The 1832 span will be several feet higher above the ground and secured with tie-down fixtures. Federal and state emergency-management agencies have awarded approximately $1.9 million to cover most of the project’s cost following a lengthy planning, engineering and historic-preservation review process. Timber framing work is expected to continue through the winter, depending on the availability of specialized lumber. Once the structural work is completed, a large crane will lift the bridge and place it on its new foundation. If all goes well, the work could be completed in the spring of 2027. |
Repairs Underway | September 2, 2026 |
| PA/38-32-05 |
Kintersburg Bridge Indiana County Indiana County Parks & Trails has secured $807,314 to restore and repair the bridge — one of only four Howe truss bridges remaining in Pennsylvania. The bridge was removed from its abutments and transported to Lancaster County Timber Frames of York, Pennsylvania for repairs. The reconstructed span was lifted by a crane and placed back on its abutments on October 27, 2026. The project is expected to be complete by Thanksgiving. |
Project Underway | October 27, 2026 |
| PA/38-39-01/td> |
Bogert's Bridge Allentown, Lehigh County, PA DDesign of the repairs to this bridge are complete and the project is underway. Construction is expected to be completed in 2027. |
Project Underway | October 8, 2026 |
|
Québec |
|||
| QC/61-01-05 |
Pont Alphonse-Normandin
TThe
bridge was moved off of its abutments in the summer of 2023 for repairs.
Repairs were completed and the structure moved back into place in the
summer of 2024. After a delay of over a year, the project got underway
again on July 14, 2025. The work was finally completed during the summer
of 2026.Abitibi-Témiscamingue Region, QC |
Repairs Completed | October 15, 2026 |
| QC/61-72-01/td> |
Pont Prud'homme Bridge
The bridge was closed to traffic for safety reasons in
May 2019. After 6 years, repair work
is now underway. On July 29, 2026, the bridge was moved to the east bank of rivière du Diable
to allow for construction of two new abutments 1.2 meters (4 feet) higher to reduce the effects of flooding and ice jams on the bridge.
Repairs to the bridge are also underway while it is sitting in dry land.
Work is expected to be completed sometime in
2027. Laurentides Region, QC |
Repairs Underway | October 8, 2026 |
|
Vermont |
|||
| VT/45-01-01 |
Salisbury Station Bridge
After being consumed by fire on September 10, 2016, plans have been in the works to construct a replica
of the historic covered bridge. Due to federal budget cuts, the project
has been delayed until 2031.Addison County, VT |
Project in Design | May 15, 2025 |
| VT/45-03-05 |
Sanborn Bridge
In the summer of 2024 the bridge was removed from ita abutments and
dismantled. The project to reconstruct it on new abutments is on
hold indefinitely.Lyndon, VT |
Project on Hold | August 15, 2026 |
| VT/45-03-07 |
Randall Bridge
Bridge closed to all traffic and use. Rehabilitation of the bridge for use
as a pedestrian and trail (snowmobile) crossing. Rehabilitation design by
DuBois & King, Inc. Work to include repair to roof framing, trusses, floor
framing, concrete abutments, and approach pathway.Lyndon, VT |
Conceptual design complete | December 17, 2022 |
| VT/45-04-05 |
Westford or Brown's River Bridge
On May 22, 2025, the Selectboard approved a contract with Vermont Heavy Timber of Huntington
for repairs to the bridge which will include repairing structural damage
to the Burr arches, bolster beams, bearing blocks and joists, as well as
flashing and sheathing utilizing protective measures to prevent future
damage.
Westford, VT |
Repairs underway | February 8, 2026 |
|
West Virginia |
|||