logoNational Society for the
Preservation of Covered Bridges

 

Bridges Under Repair

Last updated November 8, 2026

This page lists current & recent work being done on covered bridges or under design. If you are aware of any projects not included here, please notify us at nspcb@yahoo.com so they can be added.

For earlier entries, see the list of major covered bridge projects since 2010.pdf file

California Maine New Hampshire Pennsylvania
Illinois Maryland New York Québec
Indiana Missouri Ohio Vermont
Kentucky New Brunswick Ontario West Virginia

World Guide Number     Last Updated
 
Illinois
   
IL/13-06-01

Red Bridge
Princeton, IL

After being severely damaged by a tractor-trailer on November 16, 2023, a crew from the Illinois Department of Transportation installed temporary shoring in December 2023 to stabilize the roof. The structure was evaluated and repairs are underway. The project is expected to be completed in Spring 2027.

Repairs Underway October 8, 2026
 
Indiana
   
IN/14-49-07

Traders Point Bridge
Marion County, IN

On August 18, 2025, Indiana Landmarks announced that bridge was included on its annual compilation of the state’s "10 Most Endangered" landmarks. Originally built over Fishback Creek, it was moved about 0.6 miles to its present location in 1960. The bridge will be dismantled soon, repaired and reconstructed in Eagle Creek Park along a pedestrian walkway.

Project to begin soon October 28, 2026
IN/14-61-05

Nevins Bridge
Parke County, IN

The bridge was closed due to structural issues. An arch on the southwest corner of the bridge has failed, necessitating immediate repairs. No estimate when repairs will occur.

Project Underway October 8, 2026
IN/14-61-21

Portland Mills Bridge
Parke County, IN

The bridge has been closed due to the discovery of extensive termite damage on the lower chords around all of the arch terminals and on the arches themselves.  The county estimates that repairs will cost $800,000 to $1 million. According to the minutes from the December 15, 2025 meeting, the county will be seeking federal funds for more substantial repairs. We have not received any updates since then.

Repairs Anticipated December 15, 2025
IN/14-67-10  

Oakalla Bridge
Putnam County, IN

The bridge has been closed due to “structural integrity issues”. All four arch ends are being replaced. Two of them had already failed and others were not in good condition. Some of the damage is thought to be the result of an overweight vehicle crossing, probably repeatedly. The strain has caused some unusual bending of the arches and damage to the vertical posts near the ends caused by excess force from the adjoining diagonal timbers.

Repairs Underway November 8, 2026
 
Kentucky
   
 
Maine
   
 
Maryland
   
 
Missouri
   
MO/25-58-01

Locust Creek Bridge
Linn County, MO

On February 26, 2025, the bridge was moved to a new location in Pershing State Park where it will become the trailhead for the park's riparian trail. It has been waiting for approach spans to be constructed for over a year.

Awaiting Repairs October 26, 2026
 
New Brunswick
   
NB/55-14-13

Wheaton or Tantramar River #2 Bridge
Westmoreland County, NB

The bridge was closed on July 11, 2024 due to safety concerns. The New Brunswick Department of Transportation and Infrastructure is planning to install a modular bridge next to it for traffic and restore the covered bridge for pedestrian use.

Bypass Planned October 12, 2026
 
New Hampshire
   
 
New York
   
 
North Carolina
   
 
Ohio
   
OH/35-05-06

Blackwood Bridge
Athens County, OH

The extensive repairs to this bridge are now complete and the span was opened to traffic on September 18, 2026. Work included repairs to the trusses and abutments along with a new floor and new metal roof.

 Project Completed September 18, 2026
 
Ontario
   
ON/59-50-01 West Montrose Bridge
Waterloo County, ON

Repairs to this span have begun. The work will include removal of the steel Bailey truss which had provided part of the structures support along with other repairs. The project was advertised in spring 2025 and is expected to be completed in Spring 2027.

Repairs Underway October 8, 2026
 
Pennsylvania
   
PA/38-09-05 South Perkasie Bridge
Bucks County, PA

On September 2, 2026, five years after the remnants of Hurricane Ida swept the bridge from its abutments, the long-awaited repair project was officially underway. The work will fix the bridge’s historic timber structure and place it on new abutments approximately 50 feet farther from the East Branch Perkiomen Creek to reduce the risk of future flood damage. The 1832 span will be several feet higher above the ground and secured with tie-down fixtures. Federal and state emergency-management agencies have awarded approximately $1.9 million to cover most of the project’s cost following a lengthy planning, engineering and historic-preservation review process. Timber framing work is expected to continue through the winter, depending on the availability of specialized lumber. Once the structural work is completed, a large crane will lift the bridge and place it on its new foundation. If all goes well, the work could be completed in the spring of 2027.

Repairs Underway September 2, 2026
PA/38-32-05 Kintersburg Bridge
Indiana County

Indiana County Parks & Trails has secured $807,314 to restore and repair the bridge — one of only four Howe truss bridges remaining in Pennsylvania. The bridge was removed from its abutments and transported to Lancaster County Timber Frames of York, Pennsylvania for repairs. The reconstructed span was lifted by a crane and placed back on its abutments on October 27, 2026.  The project is expected to be complete by Thanksgiving.

Project Underway October 27, 2026
PA/38-39-01/td> Bogert's Bridge
Allentown, Lehigh County, PA

DDesign of the repairs to this bridge are complete and the project is underway.  Construction is expected to be completed in 2027.

Project Underway October 8, 2026
 
Québec
   
QC/61-01-05
Pont Alphonse-Normandin
Abitibi-Témiscamingue Region, QC

TThe bridge was moved off of its abutments in the summer of 2023 for repairs. Repairs were completed and the structure moved back into place in the summer of 2024. After a delay of over a year, the project got underway again on July 14, 2025. The work was finally completed during the summer of 2026.

Repairs Completed October 15, 2026
QC/61-72-01/td>
Pont Prud'homme Bridge
Laurentides Region, QC

The bridge was closed to traffic for safety reasons in May 2019. After 6 years, repair work is now underway. On July 29, 2026, the bridge was moved to the east bank of rivière du Diable to allow for construction of two new abutments 1.2 meters (4 feet) higher to reduce the effects of flooding and ice jams on the bridge. Repairs to the bridge are also underway while it is sitting in dry land. Work is expected to be completed sometime in 2027.

Repairs Underway October 8, 2026
 
Vermont
   
VT/45-01-01
Salisbury Station Bridge
Addison County, VT

After being consumed by fire on September 10, 2016, plans have been in the works to construct a replica of the historic covered bridge. Due to federal budget cuts, the project has been delayed until 2031.

Project in Design May 15, 2025
VT/45-03-05
Sanborn Bridge
Lyndon, VT

In the summer of 2024 the bridge was removed from ita abutments and dismantled.  The project to reconstruct it on new abutments is on hold indefinitely.

Project on Hold August 15, 2026
VT/45-03-07
Randall Bridge
Lyndon, VT

Bridge closed to all traffic and use. Rehabilitation of the bridge for use as a pedestrian and trail (snowmobile) crossing. Rehabilitation design by DuBois & King, Inc. Work to include repair to roof framing, trusses, floor framing, concrete abutments, and approach pathway.

Conceptual design complete December 17, 2022
VT/45-04-05
Westford or Brown's River Bridge
Westford, VT

On May 22, 2025, the Selectboard approved a contract with Vermont Heavy Timber of Huntington for repairs to the bridge which will include repairing structural damage to the Burr arches, bolster beams, bearing blocks and joists, as well as flashing and sheathing utilizing protective measures to prevent future damage. 

Repairs underway February 8, 2026
 
West Virginia