This page lists current & recent work being done on covered bridges or under design. If you are aware of any projects not included here, please notify us at nspcb@yahoo.com so they can be added.
For earlier entries, see the
list of major covered bridge projects since 2010.
California | Maine | New Hampshire | Pennsylvania |
Illinois | Maryland | New York | Québec |
Indiana | Missouri | Ohio | Vermont |
Kentucky | New Brunswick | Ontario | West Virginia |
World Guide Number | Last Updated | ||
California |
|||
CA/05-04-01 |
Honey Run Bridge The replacement for the Honey Run Bridge lost on November 8, 2018 during the devastating Camp Fire in Butte County in northern California is now complete. |
Project Completed | November 23, 2022 |
Illinois |
|||
IL/13-79-01 |
Little Mary 's River Bridge A storm tore the roof off of this bridge near Chester on July 1, 2023. After being exposed to the elements for over a year, repairs are now underway. Samron Midwest Contracting from Murphysboro, Illinois, was awarded a contract for $311,702 for the repair work. In addition to replacing the roof, they will also be adding a fire suppression and security system. |
Project Underway | June 7, 2025 |
Indiana |
|||
IN/14-23-02 |
Cades Mill Bridge The Fountain County Historical Committee has raised sufficient funds for this project. Work was completed in the spring of 2025 with a ribbon-cutting celebration on June 8, 2025. |
Repairs Complete | May 12, 2025 |
IN/14-29-14 |
Bell's Ford Bridge The Bell's Ford Bridge which originally stood in Jackson County, Indiana, has been rebuilt as a pedestrian bridge in Fishers, Hamilton County, Indiana. This is the only Post truss covered bridge. The project was completed in early 2025 with a celebration planned for the spring. |
Project Complete | May 12, 2025 |
IN/14-61-26 |
Melcher Bridge The abutments of this bridge had deteriorated to the point where they needed to be replaced. The repair project began in 2024 and is still underway. |
Project Underway | May 12, 2025 |
IN/14-70-01 |
Smith or Ewbank Bridge The project to repair this bridge began in the summer of 2024 when it was moved off of its abutments. In March 2025, with repairs nearly complete, it was placed back on its abutments. |
Project Nearly Complete | May 12, 2025 |
Kentucky |
|||
KY/17-35-04 |
Ringos Mill Bridge Sections of the upper and lower chords (particularly near the ends of the lowr chords) needed to be replaced. Some some floor joists were replaced and deteriorated sections of some vertical truss members spliced with new wood. The project is now complete and a celebration is scheduled for October 4, 2025. |
Repairs Complete. | May 12, 2025 |
KY/17-35-05 |
Grange City Bridge After spring flooding badly damaged an already crumbling abutment causing the bridge to drop a couple feet, Graton Associates were hired to perform emergency repairs. The bridge was stabilized on July 1, 2020 and underwent additional repairs in the fall of 2020. A full restoration of the bridge is now complete and a celebration is scheduled for October 4, 2025. |
Repairs Complete. | May 12, 2025 |
Maine |
|||
Maryland |
|||
Missouri |
|||
MO/25-58-01 |
Locust Creek Bridge On February 26, 2025, the bridge was moved to a new
location in Pershing State Park where it will become the trailhead for the
park's riparian trail. |
Relocation Underway | February 26, 2025 |
New Brunswick |
|||
NB/55-14-13 |
Wheaton or Tantramar River #2 Bridge The bridge was closed on July 11, 2024 due to safety concerns. The New
Brunswick Department of Transportation and Infrastructure is planning to
install a modular bridge next to it for traffic and restore the covered
bridge for pedestrian use. |
Bypass Planned | May 12, 2025 |
New Hampshire |
|||
New York |
|||
North Carolina |
|||
Ohio |
|||
OH/35-56-18 |
Knowlton or Long Bridge Monroe County commissioners have decided to replace the covered bridge which partially collapsed in July 2019. A second span collapsed in June 2020. The article did not indicate if the entire bridge was to be replaced, or only the collapsed spans. The county plans to use timber from a county-owned lot for the repairs which may go out to bid in spring 2023. |
Repairs planned | November 23, 2022 |
Ontario |
|||
PA/38-09-05 |
West Montrose Bridge Waterloo County, ON Repairs to this span ahve been designed and were advertised for bid. The work will include removal of the steel Bailey truss which had provided part of the structures support along with other repairs. The project was advertised in spring 2025. Bids are being processed. |
Repair Project Advertised | May 15, 2025 |
Pennsylvania |
|||
PA/38-09-05 |
South Perkasie Bridge Bucks County, PA Perkasie Borough, the Bucks County Covered Bridge Society and Perkasie Historical Society combined efforts to raise money and obtain grants for repairs to the bridge. The project design is complete and it is expected to go to bid soon with construction later in 2025. |
Repairs Anticipated | May 15, 2025 |
PA/38-15-01#2 |
Rudolph and Arthur Bridge Chester County, PA The historic covered bridge was washed away by floodwaters on September 1, 2021. A project is underway to construct a replica. |
Construction Underway Planned | May 15, 2025 |
PA/38-39-01 |
Bogert's Bridge Allentown, Lehigh County, PA Design of the repairs to this bridge are complete and the project has been put out to bid. Construction is exected to begin later in 2025. |
Project Advertised | May 15, 2025 |
Québec |
|||
QC/61-01-05 |
Pont Alphonse-Normandin
The
bridge was moved off of its abutments in the summer of 2023 for repairs.
Repairs were completed and the structure moved back into place in the
summer of 2024. However, the project has stalled with approach work has
not yet complete.
Abitibi-Témiscamingue Region, QC |
Work underway | May 15, 2025 |
QC/61-72-01 |
Pont Prud'homme Bridge
The bridge was closed to traffic for safety reasons in 2019. Repair work
has been delayed since then and is currently anticipated for sometime in
2026. Laurentides Region, QC |
Repairs Anticipated | May 15, 2025 |
Vermont |
|||
VT/45-01-01 |
Salisbury Station Bridge
After being consumed by fire on September 10, 2016, plans have been in the works to construct a replica
of the historic covered bridge. Due to federal budget cuts, the project
has been delayed until 2031.Addison County, VT |
Project in Design | May 15, 2025 |
VT/45-03-07 |
Sanborn Bridge
In the summer of 2024 the bridge was removed from ita abutments and
dismantled. The project to reconstruct it on new abutments is in the
design stage with advertising anticipated in the fall of 2025 and
construction to begin in the spring of 2026.Lyndon, VT |
Project in Design | May 15, 2025 |
VT/45-03-07 |
Randall Bridge
Bridge closed to all traffic and use. Rehabilitation of the bridge for use
as a pedestrian and trail (snowmobile) crossing. Rehabilitation design by
DuBois & King, Inc. Work to include repair to roof framing, trusses, floor
framing, concrete abutments, and approach pathway.Lyndon, VT |
Conceptual design complete | December 17, 2022 |
West Virginia |
|||